For eleven weeks I reported green. Every Thursday I filled in the same slide, changed a date or two, and moved on. I was not lying. Each individual thing I knew about looked survivable on its own: a late environment, a firewall change waiting on another team, one engineer stretched across two workstreams, a supplier who had gone quiet.
In week twelve all four arrived at once, and the project went red in a single meeting. What made it painful was not the news. It was that everything in the room had been visible for a month, and I had been the one deciding, quietly and by default, that none of it was worth raising yet.
The reason I kept it green was not dishonesty. It was that each item had a story attached. The environment was late, but the vendor had promised Friday. The firewall change was queued, but the other team said it was routine. Every item had a sentence that made it sound handled, and I told myself the sentence rather than the date.
What I missed is that risk is not a list of items. It is the distance between what you have committed to and what you can currently evidence. That distance had been growing for a month while the status colour stayed still, because the colour measured how I felt about the plan rather than what the plan could survive.
There was also a quieter cost. The people around me had seen the same four things. Because I never named them, they assumed I had a plan they were not party to, so nobody raised them either. Silence at the top of a project teaches everyone below it to stay silent too.
—
What I would do differently
—
The principle
Zarar Ismail
Founder of the Institute of Technical Leadership, writing from two decades of technical delivery.